Completed Projects
Completed Projects
The new parking garage and student union kitchen remodel are now complete and operational campus-wide, and the infrastructure is complete and fully functional. These improvements to the Rocklin campus were made possible by Measure E.
On this page, you can find the following completed projects:

Parking Garage
486,700 gross square feet, 101,000 square foot footprint, 5 levels
$49.9M final construction cost
Notice of completion: July 2021
Measure E funded
- 1,501 parking spaces
- 20 active electrical vehicle stations with 68 expansion stations
- Will address post-pandemic needs for parking on campus while helping to reduce traffic and parking impacts in the surrounding community
Learn more about the parking garage project
Watch 62-second time-lapse video of parking garage construction

Student Union Phase 1-Kitchen Renovation
$5M final construction cost
Notice of completion: February 2021
Measure E Funded
- Original cafeteria kitchen and serving areas in Building J, Campus Center brought to current building code requirements
- Kitchen plumbing and wiring updated
- Air handling units replaced to improve energy efficiency
- Generator added to support refrigerators/freezers in case of loss of power
Learn more about the Student Union Phase 1 – Kitchen Renovation

Infrastructure Project
Construction budget: $25M
Project budget: $32.6M
Completion: Summer 2022
Measure E funded
Upsizing or replacement of utility and technology services to all existing and new buildings
- Include electrical service, low voltage (data) service, water service (potable and non-potable), sanitary sewer, and storm water systems
- Natural gas infrastructure will be extended to the planned new construction